COMMISSIONING OF DATA ACQUISITION, PROCESSING AND ANALYSIS CENTER IN TGK-1, OPEN JSC
In March 2009 in TGK-1, Open JSC "Automated system for Center of technological data processing" is finally put in constant operation after trial performance. Monitor Electric was the general contractor.
Though the data model of TGK-1, OJSC is pretty large, all required project documentation development, equipment installation and precommissioning were done on a tight schedule.
Hardware platform of the Automated system meets all modern requirements and is realized at blade-system and disk storage. Software platform is SCADA/EMS CK-2007 which ensures integration of heterogeneous data sources and technological systems of TGK-1.
We express gratitude to customer experts who participated in the project. Thanks to their help it became possible to maintain the time of putting the system into constant operation.